Recent Site Activities
Constructing the new dividing berm in Sulfate Basin #1.
2-11-02
Excavating soil from the floor of Sulfate Basin #5.
2-12-02
Vacuuming the Floor in the Beam Storage Building in preparation for upcoming building demolition.
2-06-02
Surveying prior to constructing a new dividing berm in Sulfate Basin #1.
2-19-02