Recent Site Activities
Deploying HDPE membrane on top of the attic fill on former Sulfate Basin 3.
9-30-02
Collecting a post-decontamination concrete chip sample inside the Polymer Plant.
9-23-02
Fly Ash Stockpile as seen from the former Fly Ash Basin 6.
9-19-02
Placing attic fill on the former Sulfate Basin 4.
Air meters continuously monitor the air outside the buildings work area in Section VI.
9-18-02
United States Army Corps of Engineers demolishes Section II as seen from a nearby roof.
9-6-02