|
The Warren Sentinel Article date: May 27, 2004 Soccerplex, connector road discussed by EDA By: Roger Bianchini Several projects involving property on or adjacent to the Avtex cleanup and remediation site were discussed during the Front Royal-Warren County Economic Development Authority meeting of May 21. County Administrator Doug Stanley said the initial phase of land clearing and grading work on the much discussed, much delayed Soccerplex project is anticipated to be completed by July. FMC Remediation Manager Doug Bement has agreed to have the work done in exchange for other on-site considerations, primarily the use of fill dirt from the site. FMC Corporation, as the sole surviving former owner of the sprawling rayon and synthetic fibers manufacturing facility built in 1940, is a mandated partner in the Superfund cleanup project. The goal on the Soccerplex front is to get two to four fields into playable condition while negotiations to overcome the stalled financial involvement of the U.S. Soccer Federation continue. While the USSF has contributed $128,000 to the project, it has hedged on a larger commitment that would lead to construction of a regional tournament level facility at a seven- field complex on a non- contaminated portion to the south east of the 467- acre Superfund site. EDA staffer Jennifer McDonald noted that a $1 million revenue shown on the site Capital Improvement Plan for the Soccerplex project this year had to be deleted due to the USSF impasse. In another matter peripheral to the Avtex site Town Manager Rick Anzolut Jr. informed the EDA that discussion with Roanoke engineering firm Mattern & Craig on design aspects of a west side connector road that would run along the eastern boundary of the property were proceeding lethargically at best. Anzolut explained that a VDOT analysis of limiting environmental aspects of the project, complicated by the projected route’s proximity to the Avtex property, had only recently been received and forwarded to the engineers. The long-discussed west side bypass is proposed to run along Shenandoah Avenue past Warren Memorial Hospital on the north side of town, cut across a short portion of Kendrick Lane to a right of way between Avtex and R-MA that would connect a newly constructed two lane road to Kerfoot Avenue which continues to Criser Road on the south side of town. After nearly a year of developmental discussion Anzolut said he’d hope to progress to the design and environmental engineering phase of the project by now. “It’s just a simple negotiation on the engineering estimate on a contract. That we’re not satisfied with the figure being discussed is not unusual,” Anzolut later observed. However, he did indicate to the EDA that if the engineers cost estimate wasn’t reduced it was likely the town would be looking for another engineering partner on the project. After Anzolut commented on added costs associated with environmental liability the engineers were estimating, Bement observed, “That should be a moot issue. [FMC] owns all environmental [liability] issues, so I don’t know what the hang up would be there.” In his report on the remediation project, Bement estimated the completion “of about 50 percent” of the cleanup work on the viscose basins with basins one through eight to be tackled in the coming year. The working schedule on the cleanup and remediation shows completion of the building asbestos abatement and demolition in 2005. That work has progressed back to the Power Plant complex that will be tackled next with newly appropriated federal funds; environmental remediation in 2007; Conservancy Park development in 2010. Development of the 170-acre business park is predicted to continue through 2020. In other business the board: extended a contract with Yount, Hyde & Barbour, PC for auditing services; and agreed to apply $150,000from the sale of two lots at the Happy Creek Industrial Park to pay off the bulk of a $159,341 debt with BB&T Bank for 16-acre lot 5 at the Kelley Industrial Park. All votes were by 4-0 margins with John LaBarca and Bill Barnett absent. Michael South, appointed earlier to the week to replace the departed Bill Sealock, was also present but did not vote. South will not assume his position until after next month’s county planning commission meeting, when he will resign from the planning commission to take his seat on the EDA board. |