|
The Warren Sentinel Article date:
October 21, 2004
Avtex
Development concept approved EDA
also approves $700,000 contract for four soccer fields By: Roger
Bianchini The Front
Royal-Warren County Economic Development Authority followed up last
week’s intensive work session review of Executive Director Paul
Carroll’s Conceptual Plan for the Avtex Business Park by a 6-0 vote,
with one absence, of that plan at its Friday meeting. However, the
board’s interest was piqued when Carroll mentioned that one of six
marketing and development companies he had contacted had a history of
purchasing entire sites for redevelopment. “Wouldn’t
we be better off if we found a company that purchased such
properties, have them buy the site and come up with their own plan?”
Bill Barnett asked. “If
we can end up in the same place with us spending less money we’re
that much better off.” “If they’re
willing to come in and take our plan and work with it, modify it,
fine,” Chairman John LaBarca commented of the potential of bringing
a buyer in at an earlier stage of redevelopment. Carroll said that
while he had no problem pursuing such a developmental option, it was
his understanding that the firm in question, Cherokee Partners of
Atlanta, generally purchased Brownfield, or abandoned manufacturing
sites, at a much earlier stage of redevelopment, prior to any
remediation occurring. “I’d like to
keep the [marketing] process on two tracks,” Carroll said of keeping
the EDA’s options open in case such an early site purchase
couldn’t be accomplished. Carroll said this
week seven firms, including Cherokee Partners, which he said had over
$2 billion in assets, was being pursued as potential developers or
marketers of the approximate 170-acre Avtex Business Park ( a detailed
review of Carroll’s Conceptual Plan for the site appeared in last
week’s issue). Also at last
week’s EDA meeting the board by another 6-0 vote a $722,906 contract
with Ballard Construction to build four soccer fields at the 33-acre
Avtex SoccerPlex site. Full realization
of the envisioned seven field soccer complex that would include a
regional, professional level stadium partially funded by the United
States Soccer Foundation, remains a more distant goal, the board was
told by county staff. “I still have a
problem with spending $700,000 on four soccer fields,” EDA Board
Member Patty Wines said. “You
drive and see soccer fields anywhere.
It looks like they just cleared a cornfield, grass is grass but
I guess we got sucked into this U.S. soccer thing.
It just seems to me we’re spending $700,000 and not even
getting everything we thought we were.” Barnett pointed
to the cost of prime developmental land as driving costs up. “We would liked
to have had more bids but their bid fell right in where the estimates
we expected were,” County Administrator Doug Stanley said .
He added that original cost estimates of the SoccerPlex were as
high as $3 million and Ballard’s initial bid on four fields as
initially envisioned had was almost $1.2 million. Existing funding of
the project includes $225,000 from the county, $73,378 from the town,
$120,000 from the USSF and $20,000 from the Front Royal Soccer
Association. County
staff pointed out an additional $285,000 from the county’s
undesignated fund balance would be necessary to fund the contract with
Ballard. Some amusement
accompanied the board’s annual approval of a Happy Creek Technology
Park grazing lease to Joe Baldwin on 155 acres, including 3 acres on
Progress Drive. |