The Northern Virginia Daily
Article date:
August 22, 2008

Sewer removal nears completion at Avtex Superfund site
By Jessica
Coleman
FRONT ROYAL — With one major
project completed, another is under way at the Avtex Superfund
site.
Sewer removal is nearly
complete, said John Torrence, site manager for FMC, the company
in charge of the cleanup, with one major removal done. Now, the
major focus is the closure of viscose basins 4, 5 and 6, which
were basically landfills, he said.
The "big dig," a trench 1,200
feet long, 100 feet wide and 10 feet deep, was created to
extract 7,200 feet of sewer from the site. The excavation was
recently completed and the trench filled with soil and crushed
concrete from buildings on-site.
"There were just as many
sewers as we anticipated," Torrence said. "They were all found,
and they were all removed."
The pieces of the sewers that
were dug up are still on-site, but will soon be crushed and sent
to landfills off-site. But before that takes place, the crushed
pieces will go through a machine to sift out the soil.
"The soil doesn't need to go
to a landfill, but the concrete does," Torrence said.
"These piles will slowly
disappear," he added. "Eventually they'll all be removed or used
as fill material on the site."
The "big dig" was part of the
second phase of sewer removal. The first phase was completed in
2005 and centered on the lines in the northern part of the site.
The third phase will probably begin in 2009, Torrence said in an
earlier interview, and will focus on the sewers on the other
side of the railroad that runs through the site.
"All the sewers that are
attainable have been removed," he said, adding that some more
soil tests need to be completed before the rest of the sewers
can be removed.
On the other side of the
site, at viscose basins 4, 5 and 6, construction started in July
and is expected to be completed in October. First, the sites
were cleared. Then they were graded at a slope to allow water to
drain. A plastic layer and a cloth layer were then placed on top
of the soil, which will be covered with 2 feet of clean soil.
This fall, temporary grasses will be planted to see how things
grow, until a more permanent planting can be done in the spring.
This week, dump trucks
deposited clean soil obtained from a local source, which was in
turn spread by bulldozers. A berm, with allocated drainage
outfalls, was created around the top of each viscose basin to
direct rainwater to a "French drain" surrounding the basins.
These will direct the clean water into the Shenandoah River.
"The water is clean,"
Torrence said. "We're not going to be sending anything that's
not clean into the river. That's not allowed."
Torrence said the work at the
viscose basins is receiving the majority of attention at the
Superfund site for the time being. At this point, he said,
things are on track for a tentative completion date in 2010 for
the 160-acre commercial-industrial park area.
"There is a sense of
satisfaction when you can see the progress on this grand a
scale," Torrence said.
|