Northern Virginia Daily
April 7, 2010
Town still unsure of role with solar site
Standard Energy planning to
seek money from state
By Ben
Orcutt
FRONT ROYAL
-- As plans for a proposed solar energy farm continue to evolve,
the town remains unsure what role it may play in the project, if
any. On Tuesday,
members of the Town Council reacted to a letter they received
from Steve Lamb, a managing member of Standard Energy, the
company that is proposing to build the solar farm at Royal
Phoenix, formerly the Avtex Fibers Superfund site. "I think
with all the changes that have happened I can't agree to
anything at this time," Councilman Chris W. Holloway said. "If
they want to build a solar farm, I don't have a problem with it.
There's too many issues at this time to make a decision." Lamb says in
his April 5 letter, which was read to the council on Monday
during a work session, that Standard Energy is not seeking
funding from the town, but has requested state funding. "The only
obligation from Front Royal is to purchase the solar power
through a Power Purchase Agreement (PPA) as they would do
normally as an [American Municipal Power] member buying power,
similar to the latest hydropower purchase," Lamb says. On March 26,
the Front Royal-Warren County Economic Development Authority
voted to approve a three-year contract to allow Standard Energy
to build a 40-acre solar farm at the Avtex site, contingent on
it being approved by FMC Corp., the former site owner, and the
U.S. Environmental Protection Agency, which is overseeing
cleanup operations. The contract
stipulates that within 180 days after its effective date,
Standard Energy must have at least 100 permanent, full-time
employees and that the company's assembly plant must be located
within town limits. Asked
Tuesday if Standard Energy would agree to the stipulation on the
number of full-time employees, Lamb said his company is not at
that stage of the lease negotiation process yet. In October,
Lamb, the majority shareholder of Standard Solar in Prior plans
called for Greg Horton, owner of Arctic Air Refrigeration in
Front Royal, and Leesburg developer William Lauterbach to
partner on the project under the name SolAVerde. "There's a
different horse in the race now," Councilman Carson C. Lauder
said. "I think the whole thing hinges on financing and it looks
like to me like Standard Energy is seeking some financing from
the state of Councilman
Thomas E. Conkey spoke in a similar vein. "This thing
started off as an idea, but it's like any other proposal, it
starts with an idea and the idea evolves and then it becomes a
formal business arrangement," Conkey said. "We're somewhere
between the idea and the formal business arrangement. The bottom
line is, we're going to do what's best for the town and that may
mean some sort of solar and it may not. We don't know at this
point." Councilman
N. Shae Parker echoed sentiments previously expressed by Vice
Mayor Bret W. Hrbek, that the key is the jobs that Standard
Energy may bring to the town. Other than
that, it's still too early, Parker said, for the town to decide
what role it will play, including the possibility of purchasing
solar power from Standard Energy. "I think at
this stage of the game there are still more questions than
answers," Parker said. Councilman
Thomas H. Sayre agreed that jobs are a key component of the
project, but added that he has concerns about how the process
has been handled.
"Unfortunately, there's been a lack of transparency in our local
government," Sayre said. |